Out of Scope
Customs Reporting like I-95, I-408 as it that potentially requires more personal details and crew effects in the system
Integrations built by Adonis to third parties
Competences & Requirements, Next of Kin or similar personal Information
Employee Portal
Onboard modules besides planning Planning and Crew Change
Sample Timeline
...
The below timeline indicates that the full specification of the needed API functionality is started upon contract signature
The kick-off, 3-5 days, will be performed onsite with dedicated customer resources made available
A second onsite visit, most often needed when we get to the User Acceptance Testing can be planned for
The Customer will prepare the environments and have the installations along with user access to the application in place by kick-off
The kick-off, 3-5 days, will be performed onsite with dedicated customer resources made available
There is no need for standard data migration, as all persons will come in via the API
Vessel Installations can be performed at the same time as the configuration.
Adonis can perform installations as long as the environment is prepared and proper remote connections and access are provided
A staged roll-out for the vessels is not planned for but can be done, together with the customer
The customer is responsible for their own Documentation, User Acceptance Testing, and End User TrainingA second onsite visit in relation to the User Acceptance Testing can be planned for
Adonis is willing to do End User training, however, this is not included in the cost or time estimates.
A delay in the contract signature can result in a delay in the Project mobilization and the Go live. December is a month where resources often take vacations, and can by such prolong the implementation phase.