In the below articles you find a description of the Adonis Project Delivery Methodology and other useful information
...
https://adonishr.atlassian.net/l/cp/aW4AVszP
Scope
In Scope
API
Inserting data
Adonis will copy and make the necessary API methods to insert the below data available in dedicated customer APIs. The cost is part of the quotation
Personal Data limited to
Trips as
Voyages (see below)
Port dates/Itinerary
Extracting Data
The customer will use the existing method for extracting data from the system as described in the following document and chapter:
https://adonishr.atlassian.net/wiki/spaces/UD/pages/3645079565/AdonisWebServices+-+Consume+example#Example-consume-DB-views-via-API-(AdonisIntegrationWebService)
Database views will be scoped and created together with Adonis technical consultants during the project phase
Planning Module
The customer will create a Trip as a Voyage via existing API calls. A Voyage is similar to a Project but has more functionality around it. By moving a Voyage start date, one can also move the Onboard activity start date for all linked persons accordingly.
Inside a Voyage (Trip) there can be several port calls, as needed for Crew Changes
Adonis suggests that a plan is created manually by the users. By using the Voyage a user can not assign persons to shifts outside the Voyage dates. There is easy functionality to copy previous plans.
The planning is linked to the Crew Change module that will be used onboard.
There are existing API calls for creating Voyages, however, a new API for creating the ports is needed.
It is still possible for the customer to create one plan per trip as wanted.
...
Crew Change
The system will be made available for onboard users.
An onboard role will be responsible for confirming the Onboard activities at the date the person sign on, and the same upon sign off
Out of Scope
Customs Reporting that potentially requires more personal details and crew effects in the system
Integrations built by Adonis to third parties
Competences & Requirements, Next of Kin or similar personal Information
Employee Portal
Onboard modules besides Planning and Crew Change
Sample Timeline
The sample timeline is based on the scope discussed in our meeting on the 14th of July 2022.
The below timeline indicates that the full specification of the needed API functionality is started upon contract signature
The kick-off, 3-5 days, will be performed onsite with dedicated customer resources made available
A second onsite visit, most often needed when we get to the User Acceptance Testing can be planned for
The Customer will prepare the environments and have the installations along with user access to the application in place by kick-offThe kick-off, 3-5 days, will be performed onsite with dedicated customer resources made available
There is no need for standard data migration, as all persons will come in via the API
Vessel Installations can be performed at the same time as the configuration.
Adonis can perform installations as long as the environment is prepared and proper remote connections and access are provided
A staged roll-out for the vessels is not planned for but can be done, together with the customer
The customer is responsible for their own Documentation, User Acceptance Testing, and End User TrainingA second onsite visit in relation to the User Acceptance Testing can be planned for
Adonis is willing to do End User training, however, this is not included in the cost or time estimates.
A delay in the contract signature can result in a delay in the Project mobilization and the Go live. December is a month where resources often take vacations, and can by such prolong the implementation phase.
Roadmap Planner |
---|
maplinks | b784fb81-ce67-4c3b-8f60-97954dd801cd~~~~~8349d40e-955c-4dfe-9640-806b6535c3ee~~~~~ab972012-d79f-4abb-8da2-82cc0ea17389 |
---|
timeline | true |
---|
source | %7B%22title%22%3A%22Roadmap%20Planner%22%2C%22timeline%22%3A%7B%22startDate%22%3A%222022-08-14%2000%3A00%3A00%22%2C%22endDate%22%3A%222023-02-28%2000%3A00%3A00%22%2C%22displayOption%22%3A%22WEEK%22%7D%2C%22lanes%22%3A%5B%7B%22title%22%3A%22Mobilization%22%2C%22color%22%3A%7B%22lane%22%3A%22%23f15c75%22%2C%22bar%22%3A%22%23f58598%22%2C%22text%22%3A%22%23ffffff%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22rowIndex%22%3A0%2C%22startDate%22%3A%222022-08-14%2022%3A20%3A11%22%2C%22id%22%3A%22b58dd94a-6633-41ed-bbab-0d0b7600e363%22%2C%22title%22%3A%22Project%20Mobilization%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1.9801980198019802%2C%22pageLink%22%3A%7B%7D%7D%5D%7D%2C%7B%22title%22%3A%22Technical%22%2C%22color%22%3A%7B%22lane%22%3A%22%23654982%22%2C%22bar%22%3A%22%238c77a1%22%2C%22text%22%3A%22%23ffffff%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22title%22%3A%22Installation%20Office%22%2C%22description%22%3A%22This%20is%20the%20first%20bar.%22%2C%22startDate%22%3A%222022-08-22%2006%3A39%3A12%22%2C%22duration%22%3A1.881188118811881%2C%22rowIndex%22%3A0%2C%22id%22%3A%22b784fb81-ce67-4c3b-8f60-97954dd801cd%22%2C%22pageLink%22%3A%7B%22id%22%3A%223647307769%22%2C%22spaceKey%22%3A%22UD%22%2C%22title%22%3A%22Adonis%20System%20Architecture%20and%20Technical%20Requirements%22%2C%22type%22%3A%22page%22%2C%22wikiLink%22%3A%22%5BUD%3AAdonis%20System%20Architecture%20and%20Technical%20Requirements%5D%22%7D%7D%2C%7B%22title%22%3A%22API%20Development%22%2C%22description%22%3A%22This%20is%20the%20second%20bar.%22%2C%22startDate%22%3A%222022-08-15%2004%3A59%3A24%22%2C%22duration%22%3A9.96039603960396%2C%22rowIndex%22%3A1%2C%22id%22%3A%228349d40e-955c-4dfe-9640-806b6535c3ee%22%2C%22pageLink%22%3A%7B%22id%22%3A%224563665441%22%2C%22spaceKey%22%3A%22UD%22%2C%22title%22%3A%22Demo%20API%20Template%20Project%22%2C%22type%22%3A%22page%22%2C%22wikiLink%22%3A%22%5BUD%3ADemo%20API%20Template%20Project%5D%22%7D%7D%2C%7B%22rowIndex%22%3A2%2C%22startDate%22%3A%222022-10-10%2009%3A58%3A48%22%2C%22id%22%3A%226fe1f670-5b67-43a5-87c1-0beb63f2d859%22%2C%22title%22%3A%22Vessel%20Installations%22%2C%22description%22%3A%22%22%2C%22duration%22%3A2.00990099009901%2C%22pageLink%22%3A%7B%7D%7D%5D%7D%2C%7B%22title%22%3A%22Setup%20%26%20Configuration%22%2C%22color%22%3A%7B%22lane%22%3A%22%233b7fc4%22%2C%22bar%22%3A%22%236c9fd3%22%2C%22text%22%3A%22%23ffffff%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22title%22%3A%22User%20Access%20(Includes%20all%20office%20%26%20onboard%20access%20groups)%22%2C%22description%22%3A%22This%20is%20the%20third%20bar.%22%2C%22startDate%22%3A%222022-09-04%2017%3A20%3A47%22%2C%22duration%22%3A5%2C%22rowIndex%22%3A0%2C%22id%22%3A%22ab972012-d79f-4abb-8da2-82cc0ea17389%22%2C%22pageLink%22%3A%7B%22id%22%3A%224444422263%22%2C%22spaceKey%22%3A%22AO%22%2C%22title%22%3A%22Getting%20started%20with%20your%20Adonis%20Products%22%2C%22type%22%3A%22page%22%2C%22wikiLink%22%3A%22%5BGetting%20started%20with%20your%20Adonis%20Products%5D%22%7D%7D%2C%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222022-09-04%2019%3A00%3A35%22%2C%22id%22%3A%221a91e41a-174e-42f4-80b2-3f210a832c26%22%2C%22title%22%3A%22Basic%20Set%20Up%20and%20Configuration%22%2C%22description%22%3A%22%22%2C%22duration%22%3A6.7227722772277225%2C%22pageLink%22%3A%7B%7D%7D%5D%7D%2C%7B%22title%22%3A%22Testing%20%26%20Documentation%22%2C%22color%22%3A%7B%22lane%22%3A%22%23f6c342%22%2C%22bar%22%3A%22%23fadb8e%22%2C%22text%22%3A%22%23594300%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222022-11-07%2006%3A04%3A09%22%2C%22id%22%3A%225f13c34a-6e3c-4d5b-991d-246c142355ac%22%2C%22title%22%3A%22End%20User%20Training%22%2C%22description%22%3A%22%22%2C%22duration%22%3A3.910891089108911%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A0%2C%22startDate%22%3A%222022-10-17%2017%3A01%3A48%22%2C%22id%22%3A%2250cf24ca-e1da-4d26-a91f-747e5b76713d%22%2C%22title%22%3A%22Documentation%22%2C%22description%22%3A%22%22%2C%22duration%22%3A2.801980198019802%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A2%2C%22startDate%22%3A%222022-11-21%2012%3A18%3A24%22%2C%22id%22%3A%224e3ca5bd-d2c2-421b-a75e-c1cac45d7992%22%2C%22title%22%3A%22User%20Acceptance%20Testing%22%2C%22description%22%3A%22%22%2C%22duration%22%3A1.7920792079207921%2C%22pageLink%22%3A%7B%7D%7D%5D%7D%2C%7B%22title%22%3A%22Go%20Live%22%2C%22color%22%3A%7B%22lane%22%3A%22%238eb021%22%2C%22bar%22%3A%22%23aac459%22%2C%22text%22%3A%22%23ffffff%22%2C%22count%22%3A1%7D%2C%22bars%22%3A%5B%7B%22rowIndex%22%3A0%2C%22startDate%22%3A%222022-10-24%2000%3A24%3A57%22%2C%22id%22%3A%2238da0720-ae83-4192-aed0-f232f15fffd9%22%2C%22title%22%3A%22Prepare%20Roll-Out%20Schedule%22%2C%22description%22%3A%22%22%2C%22duration%22%3A3.98019801980198%2C%22pageLink%22%3A%7B%7D%7D%2C%7B%22rowIndex%22%3A1%2C%22startDate%22%3A%222022-12-05%2007%3A19%3A00%22%2C%22id%22%3A%226ccd5c79-e23a-432c-a581-cc39e3a873de%22%2C%22title%22%3A%22Go%20Live%20%20-%20Cooling%20Down%22%2C%22description%22%3A%22%22%2C%22duration%22%3A3.9603960396039604%2C%22pageLink%22%3A%7B%7D%7D%5D%7D%5D%2C%22markers%22%3A%5B%7B%22title%22%3A%22Kick-off%22%2C%22markerDate%22%3A%222022-09-04%2015%3A40%3A59%22%7D%2C%7B%22markerDate%22%3A%222022-12-04%2021%3A20%3A11%22%2C%22title%22%3A%22Go%20Live%22%7D%2C%7B%22markerDate%22%3A%222022-11-06%2019%3A40%3A23%22%2C%22title%22%3A%22Approval%20%26%20Readiness%22%7D%2C%7B%22markerDate%22%3A%222022-08-14%2022%3A19%3A01%22%2C%22title%22%3A%22Contract%20Signature%22%7D%5D%7D |
---|
pagelinks | UD:Adonis System Architecture and Technical Requirements~~~~~UD:Demo API Template Project~~~~~AO:Getting started with your Adonis Products |
---|
title | Roadmap%20Planner |
---|
hash | 7e585f91b31c7e8f8d7d0bb9ec8109d7 |
---|
|
In the following article, you find full information and instructions on how to get started with your Adonis Products. https://adonishr.atlassian.net/l/cp/vp7ZcAYk
The following chapters and information will be relevant for American Seafoodsthe Customer.
Technical Requirements and Installations
Preparation of data
Defining General Codes
General Codes is used as a term for pre-defined codes that will be used throughout the system in various drop-down tables and similar.
...